And you thought you had heard the end of gutter talk… Not so.
The main event the week of 9 April was cleaning, re-hanging, and placing
screening over the top of the gutters - on the back of the main house, and
cleaning and screening the gutters on the side.
The gutters were full of leaves from the lovely shade trees near the
house. The gutters in the back needed a
steeper pitch for guiding the water into a 55 gallon drum and then into the
cistern.
This system is
the principal way that water is collected for drinking, bathing, flushing and
clothes washing here at the compound. We
understand from our hosts that many do not even have this system. They must go to a river or stream to get
water. There are a few boreholes around
town where water can be bought, but that is a last resort option, especially
when money is tight for most folks.
Kananga |
Kananga traffic cop |
Relaxing on the curb |
Before starting
the project Francois took us into Kananga to look for screening. We did find suitable screening and took the
information back to Jacques. We stopped
by the shop where the last two of the six beds made for the guest house are
nearing completion. They will be ready
for pick-up tomorrow. We also visited a
brick maker to gather information on the cost for him to make the bricks now
needed to resuscitate the collapsed cistern.
The brick looked very well make and sturdy. Jacques hasn’t yet decided how he will have
the bricks made this time.
High wire act |
So… it’s back to
the high wire act, but rigged up outside on a trailer, 3.5 feet off the ground
- 55 gallon rain barrels, a Rubbermaid trunk on top of each, the extension
ladder laid between the two towers, and boards place on top of the ladder
rungs. For one part of the operation we
even had a wooden trunk on top of the ladder.
Sue didn’t get a photo of this, she was too busy stabilizing the tower
and praying there would be no great fall.
Francois and the generator |
After removing
the gutters in the back, wooden blocks were installed to hang the gutter
supports. Francois brought out a small
generator, drilled the holes in the wood, Sue put nails in the holes and handed
the “package” to Jim on the “high wire”.
A string line was then run from the high point to the new low point for
bracket installation guidance. Holes
were then drilled in each block at that line.
All we needed now was wood screws for the brackets. This required another trip into town.
5 meters measured out with a little help |
We stopped at the
hardware store first and bought the screening for the gutters. The roll of green, square grid screen was
taken out on the sidewalk in front of the store and laid down. Five meters of screening was rolled out,
measured and cut, with help here and there from a passersby. $35 for the five meters.
The market |
Next stop - the
open air market, as the hardware store didn’t have the size screws needed. As we started down the row of mostly salvaged
parts, all eyes were on us. Francois
asked a vendor for small wood screws and some are produced, but not what we
needed. As we progressed along, the word
goes out that we want wood screws of a smallish size. A woman vendor appears with about the right
size screws and another comes right along with another offering. We select 30 screws from one of the women,
paying about $3 in Congolese Francs. On
the way home we stopped at the gas station market, the only place we’ve found
Coke Lights. We bought a six pack, a
real treat. The cost about $7. We’ll probably only have one every other night
- stretching out the enjoyment…
Brackets installed |
Back at the
compound, we cut the wire screening into five, one meter sections. Jim installed the brackets and we were done
for the day. We enjoyed the Coke Lights
that night to a show of cloud lightning off in the distance, constant, bright
and silent. Nice… The next day was, unexpectedly, a day of
rest, as it rained off and on much of the day.
We “harvested” the rain barrels outside the guest house, filling up the
water tanks in both bathrooms.
Gutter cutting |
The next morning Jacques,
Francois, Jim and Sue were ready to finish the gutter work. First thing, a gutter section fell off the
trailer and cracked. Now what? Two plastic pieces were found, cut and placed
both inside and outside the cracked section using very old, very hard putty
softened with kerosene. We’re back in
business. Three one meter long gutter
sections were returned to the newly hung brackets, the screening was installed
over the gutter top and bent down both side then secured with wire wound around
the screen and gutter at half meter intervals.
This is when we added the trunk on top of the ladder and walk
boards.
Working on the down spout |
In the afternoon,
the gutter down spout leading to the rain barrel and ultimately the cistern was
cut and reattached at the gutter’s new, lower position. To clean out the gutters on the side of the
house the trailer was moved and the scaffolding was reassembled. Now we had, in addition to the four morning
workers, also two to three young men who helped steady the scaffolding
barrels. We also gained one or two
observers. These gutters were cleaned
out while in place, screened and secured.
It was a wrap by 6:30 p.m.
Since this day we
have been checking the cistern levels.
The depth has, at least, doubled, so far...
This is more than I've ever known about gutters! Sue, you must now be ready to build your own house somewhere back in Portsmouth when you sell your old one! You must be so physically fit after this experience. I know you'll be leaving very soon and I shall miss these exotic photos and interesting write ups. Thanks!!!
ReplyDeleteThat seems like a good alternative source of water, especially since an organized water distribution system seems to be out of the question. Hopefully the cistern has enough space to contain large amounts of water during the rainy season so it can sustain itself during the dry one.
ReplyDeleteMaricela Milum
This comment has been removed by the author.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteThat’s a good way of getting running water. With the rainy season coming along, it should be an easy thing to gather enough water to last for a while. My concern is how they’re maintaining the gutters, as dirt or other things can get stuck in there, or worse, mix with the water they’re gathering.
ReplyDeleteTerry Arnold @ Integrity Alaska